Free C-10 Practice Questions: Contracts & Change Orders
60 free questions with answers, explanations and the source for each. Answer one to see why. No sign-up.
0 of 0 right · 60 to go
1 / 60
According to the 'Note About Extra Work and Change Orders,' an extra-work or change order becomes an enforceable part of the contract only when it is:
A change order becomes part of the contract only when prepared in writing and signed by the parties prior to commencement of the changed work.
Source: B&P §7159
2 / 60
Under SB 800, a builder must give the buyer a minimum express written limited warranty on "fit and finish" items such as cabinets, paint, flooring, and countertops lasting at least:
Civil Code 900: as to fit and finish items, a builder shall provide a homebuyer with a minimum one-year express written limited warranty covering cabinets, mirrors, flooring, interior and exterior walls, countertops, paint finishes, and trim.
Source: Civil Code §900
3 / 60
When a buyer cancels within the cancellation period, the cancellation is honored:
The Notice of Cancellation in Civil Code 1689.7 tells the buyer: you may cancel this transaction, without any penalty or obligation, within three business days.
Source: Civil Code §1689.7
4 / 60
A licensed contractor runs an ad with no license number in it. BPC 7030.5 says every licensee shall include the license number in:
BPC 7030.5 says every licensee shall include the license number in all construction contracts, subcontracts and calls for bid, and all forms of advertising, as prescribed by the registrar. An ad without it breaks that rule.
Source: B&P §7030.5
5 / 60
A homeowner files a complaint with CSLB. According to the CSLB law book, CSLB can order the contractor into a mandatory CSLB arbitration when the alleged damages are:
The CSLB law book says CSLB offers two free arbitration programs, and when the alleged damages are less than $25,000, CSLB can order the contractor into a mandatory CSLB arbitration; disputes between $25,000 and $50,000 go to the voluntary program.
Source: CSLB Law Book p.72
6 / 60
A contract qualifies as a home solicitation contract only if it is for an amount of at least:
The statute sets the qualifying threshold at twenty-five dollars ($25) or more, including any interest or service charges.
Source: Civil Code §1689.5
7 / 60
On a service and repair contract, a contractor wants to bill the customer a trip charge and also a separate inspection fee. Under BPC 7159.14, the contractor may charge:
BPC 7159.14 says a service and repair contractor shall charge only one service charge, and a service charge includes charges such as a service or trip charge, or an inspection fee.
Source: BPC 7159.14
8 / 60
The buyer's three-business-day cancellation clock on a home improvement contract begins to run when:
Cancellation rights run from when the buyer receives the signed and dated copy of the contract, which the contractor must provide before work starts.
Source: Civil Code §1689.6 / B&P §7159
9 / 60
A change order is:
BPC 7159 says a change-order form for changes or extra work becomes part of the contract only if it is in writing and signed by the parties prior to the commencement of any work covered by the change order.
Source: B&P §7159
10 / 60
The Right to Repair Act (SB 800) generally applies to:
Civil Code §938 states the title applies only to new residential units where the purchase agreement with the buyer was signed by the seller on or after January 1, 2003. It does not cover commercial buildings, mere remodels/additions, or rental disputes.
Source: Civil Code §938
11 / 60
A change order should be signed:
BPC 7159 says a change order becomes part of the contract only if it is in writing and signed by the parties prior to the commencement of any work covered by the change order.
Source: B&P §7159
12 / 60
After cancellation, the buyer must take reasonable care of goods still in their possession, but during that period the goods are:
The buyer must take reasonable care of the goods before cancellation and during the 20-day period, but the goods remain at the seller's risk while awaiting reclamation.
Source: Civil Code §1689.11
13 / 60
On a $50,000 home improvement contract, the maximum lawful down payment is:
BPC 7159.5 caps the downpayment at one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less. 10 percent of $50,000 is $5,000, which is more than $1,000, so $1,000 is the limit.
Source: B&P §7159.5
14 / 60
A contract for an illegal purpose is:
Civil Code 1598: where a contract has but a single object, and that object is unlawful, whether in whole or in part, the entire contract is void.
Source: Civil Code §1598 / §1667
15 / 60
Civil Code 1550 lists what is essential to the existence of a contract: parties capable of contracting, their consent, a lawful object, and a sufficient cause or:
Civil Code 1550: it is essential to the existence of a contract that there should be parties capable of contracting, their consent, a lawful object, and a sufficient cause or consideration.
Source: Civil Code §1550
16 / 60
Under BPC 7085, the CSLB registrar can help resolve a dispute between a licensee and a complainant by referring it to:
BPC 7085 says the registrar may, with the concurrence of both the licensee and the complainant, refer the alleged violation and any dispute between them to arbitration.
Source: CSLB dispute resolution
17 / 60
In addition to describing the scope of the change and the added or subtracted cost, a written change order must state:
BPC 7159 says a change order is not enforceable against a buyer unless it identifies in writing, before the work starts, the scope of work, the amount to be added or subtracted, and the effect the order will make in the progress payments or the completion date.
Source: B&P §7159
18 / 60
Under BPC 7027.2, a person without a contractor's license may advertise for construction work only if the aggregate contract price is less than one thousand dollars ($1,000) and the ad:
BPC 7027.2 lets a person who is not licensed advertise for construction work only if the aggregate contract price is less than one thousand dollars ($1,000) and the person states in the advertisement that the person is not licensed.
Source: B&P (unlicensed advertising disclosure)
19 / 60
'Consideration' in a contract means:
Civil Code 1605: any benefit conferred, or agreed to be conferred, upon the promisor, to which the promisor is not lawfully entitled, or any prejudice suffered by the other person, as an inducement to the promisor, is good consideration for a promise.
Source: Civil Code §1550 / §1605
20 / 60
Under the Right to Repair Act, the outside deadline to bring an action for a defect in new residential construction is generally:
Civil Code 941(a): except as specifically set forth in the title, no action may be brought to recover under it more than 10 years after substantial completion of the improvement.
Source: Civil Code §941(a)
21 / 60
A buyer of a home improvement contract may generally cancel until midnight of the:
A covered home-improvement buyer may cancel until midnight of the third business day.
Source: Civil Code §1689.6(a); B&P §7159
22 / 60
A home improvement contract generally gives the buyer a right to cancel within:
Civil Code 1689.6(a)(2) gives the buyer the right to cancel until midnight of the third business day, or the fifth business day if the buyer is a senior citizen, after the buyer receives a signed and dated copy of the contract.
Source: Civil Code §1689.7 (3-day cancellation)
23 / 60
A home improvement contract must include a notice titled:
The contract must include the statutory notice headed 'Mechanics Lien Warning.'
Source: B&P §7159
24 / 60
Before any work starts, the contractor must give the buyer:
The contractor must provide a copy signed and dated by both parties before work starts.
Source: B&P §7159
25 / 60
The maximum down payment on a home improvement contract is:
BPC 7159.5: if a downpayment will be charged, it shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less.
Source: B&P §7159.5
26 / 60
Which pair of conditions is required for a valid service and repair contract under B&P §7159.10?
A service and repair contract requires that the buyer initiated contact and that no payment is due or accepted until the work is completed (no down payment).
Source: B&P §7159.10
27 / 60
The contract's schedule of progress payments must:
BPC 7159 requires the heading "Schedule of Progress Payments," and each progress payment must be stated in dollars and cents and specifically reference the amount of work or services to be performed and materials and equipment to be supplied.
Source: B&P §7159
28 / 60
The contractor must sign and give the buyer a copy of the contract:
Before work starts, the contractor must give the buyer a copy signed and dated by both parties.
Source: B&P §7159
29 / 60
A payment schedule that demands most of the money before work is done is:
BPC 7159.5: except for a downpayment, the contractor shall neither request nor accept payment that exceeds the value of the work performed or material delivered.
Source: B&P §7159 / §7159.5
30 / 60
On an 8,000 dollar home improvement contract, the maximum allowed downpayment is:
BPC 7159.5 caps the downpayment at one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less. 10 percent of 8,000 dollars is 800 dollars, which is less, so 800 dollars is the limit.
Source: B&P §7159.5
31 / 60
Under Civil Code 1556, minors (under 18):
Civil Code 1556: all persons are capable of contracting, except minors, persons of unsound mind, and persons deprived of civil rights.
Source: Civil Code §1556
32 / 60
The 'Statute of Frauds' requires certain contracts to be:
Civil Code 1624(a), the Statute of Frauds, says the contracts it lists are invalid unless they, or some note or memorandum of them, are in writing and subscribed by the party to be charged or that party's agent.
Source: Civil Code §1624
33 / 60
A home improvement contract must include a description of:
BPC 7159 requires the heading "Description of the Project and Description of the Significant Materials to be Used and Equipment to be Installed," followed by a description of the project and of the significant materials to be used and equipment to be installed.
Source: B&P §7159
34 / 60
A homeowner signs a home improvement contract at their kitchen table. Under California law, by when may the (non-senior) buyer cancel without penalty?
A home solicitation/home improvement buyer may cancel until midnight of the third business day after receiving a signed, dated copy of the contract.
Source: Civil Code §1689.6 / B&P §7159
35 / 60
If mailed, a notice of cancellation is effective:
A mailed cancellation is effective when properly addressed and deposited with prepaid postage — not when received.
Source: Civil Code §1689.6(e)
36 / 60
A home improvement contract must state the:
The contract must state approximate start and completion dates.
Source: B&P §7159
37 / 60
A homeowner signs a $4,000 home improvement contract. Under BPC 7159.2, the only kind of security interest in the home's real property that this contract may involve is:
BPC 7159.2 says no home improvement contract of a value of five thousand dollars ($5,000) or less shall provide for a security interest in real property, except for a mechanic's lien or other interest in property that arises by operation of law.
Source: BPC 7159.2
38 / 60
The total contract price must be:
BPC 7159(d) requires the heading "Contract Price," followed by the amount of the contract in dollars and cents.
Source: B&P §7159
39 / 60
In California, the maximum amount a natural person (an individual) may sue for in small claims court is:
CCP 116.221: the small claims court has jurisdiction in an action brought by a natural person if the amount of the demand does not exceed twelve thousand five hundred dollars ($12,500).
Source: Code of Civil Procedure §116.221
40 / 60
Under BPC 7091, a "latent act or omission" in construction work is one that is:
BPC 7091 defines a "latent act or omission" as an act or omission that is not apparent by reasonable inspection.
Source: CCP §337.15(b)
41 / 60
The buyer's cancellation period begins to run when:
The cancellation period starts when the buyer receives the signed and dated contract copy containing the required notice.
Source: B&P §7159; Civil Code §1689.6
42 / 60
The statute of limitations to sue on a WRITTEN contract in California is:
CCP 337(a): an action upon any contract, obligation or liability founded upon an instrument in writing must be brought within four years.
Source: CCP §337
43 / 60
Under SB 800, before a homeowner may file suit against the builder for a covered defect, the homeowner must first:
Civil Code 910: before filing an action for a violation of the Chapter 2 standards, the claimant shall initiate prelitigation procedures, starting with written notice to the builder by certified mail, overnight mail, or personal delivery.
Source: Civil Code §910 (with §§916–918 inspection/offer to repair)
44 / 60
The contract must include the contractor's:
The contract must state the contractor's name, business address, and license number.
Source: B&P §7159
45 / 60
The statute of limitations for a PATENT construction defect is:
CCP 337.1(a): no action may be brought for a patent deficiency more than four years after the substantial completion of the improvement.
Source: CCP §337.1(a)
46 / 60
A home improvement contract includes a separate finance charge between the contractor and the homeowner. Under BPC 7159.5, the finance charge must be:
BPC 7159.5 says the contract amount includes the entire cost, including profit, labor, and materials, but excluding finance charges, and a separate finance charge shall be set out separately from the contract amount.
Source: BPC 7159.5
47 / 60
If the buyer of a home improvement contract is a senior citizen (65 or older), the right-to-cancel period is extended to:
Civil Code 1689.6(a)(2) extends the right to cancel to midnight of the fifth business day if the buyer is a senior citizen, and 1689.5(f) defines a senior citizen as an individual who is 65 years of age or older.
Source: Civil Code §1689.6
48 / 60
A 'liquidated damages' clause sets:
Civil Code 1671(b): a provision in a contract liquidating the damages for the breach of the contract is valid unless the party seeking to invalidate it establishes that it was unreasonable under the circumstances existing when the contract was made.
Source: Contract law (liquidated damages)
49 / 60
The maximum downpayment on a home improvement contract is:
BPC 7159.5: the downpayment shall not exceed one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less.
Source: B&P §7159.5 / §7159(d)(8)
50 / 60
On a $30,000 home improvement contract, the maximum allowed down payment is:
BPC 7159.5 caps the downpayment at one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less. 10 percent of $30,000 is $3,000, which is more than $1,000, so $1,000 is the limit.
Source: B&P §7159.5
51 / 60
In California, a home improvement contract must be:
A home improvement contract must be in writing and signed by the parties before work begins.
Source: B&P §7159
52 / 60
After making a progress payment, a homeowner asks the contractor for lien releases covering the work already paid for. Under BPC 7159.5, until those releases are furnished, the homeowner:
BPC 7159.5 requires the contractor, if requested, to furnish a full and unconditional release from potential lien claims for any portion of the work that has been paid for, and the homeowner may withhold all further payments until these releases are furnished.
Source: BPC 7159.5
53 / 60
Under B&P §7031, an UNLICENSED contractor who performed work requiring a license generally:
BPC 7031(a) bars a contractor from suing to collect compensation for work that requires a license without alleging they were duly licensed at all times during the work. 7031(b) lets a person who used an unlicensed contractor sue to recover all compensation paid to that contractor.
Source: B&P §7031
54 / 60
A 'change order' is:
BPC 7159 says a change-order form for changes or extra work becomes part of the contract only if it is in writing and signed by the parties prior to the commencement of any work covered by the change order.
Source: B&P §7159 (change orders)
55 / 60
To cancel, the buyer must give the seller:
Civil Code 1689.6(d): cancellation occurs when the buyer gives written notice of cancellation to the seller at the address or email address specified in the agreement. A phone call is not written notice.
Source: Civil Code §1689.6(d)
56 / 60
On a 5,000 dollar home improvement contract, the maximum lawful downpayment is:
BPC 7159.5 caps the downpayment at one thousand dollars ($1,000) or 10 percent of the contract amount, whichever amount is less. 10 percent of 5,000 dollars is 500 dollars, which is less, so 500 dollars is the limit.
Source: B&P §7159.5
57 / 60
A home improvement contract AND any changes (change orders) to it must be:
Change orders must be written and signed by the parties before the changed/extra work starts.
Source: B&P §7159
58 / 60
How is the cancellation deadline for a home solicitation contract counted?
The period is measured in business days and runs until midnight of the third business day after the day the buyer signs the agreement, not by calendar days.
Source: Civil Code §1689.6(a)
59 / 60
A 'patent' construction defect is one that is:
CCP 337.1(e) defines a "patent deficiency" as a deficiency which is apparent by reasonable inspection.
Source: CCP §337.1(e)
60 / 60
A contract to repair residential damage from a declared disaster may be cancelled until midnight of the:
Civil Code 1689.6(c) lets the buyer cancel a contract for the repair or restoration of residential premises damaged by a disaster until midnight of the seventh business day after the buyer signs and dates the contract.