Free C-10 Practice Questions: Estimating, Bidding & Project Management

60 free questions with answers, explanations and the source for each. Answer one to see why. No sign-up.

0 of 0 right · 60 to go
  1. 1 / 60

    A balance sheet shows:

  2. 2 / 60

    To compare its financial data with that of other businesses within the same industry, a contractor can get industry data from organizations such as:

  3. 3 / 60

    Which group of expenses does the CSLB law book say overhead normally includes?

  4. 4 / 60

    Retention funds are not available for use elsewhere in the business while they are held. According to the CSLB law book, the contractor must therefore often finance the costs:

  5. 5 / 60

    The CSLB law book names four typical types of contractual agreements between builder and owner: the lump-sum, the cost-plus, the unit-price, and the:

  6. 6 / 60

    A 'payment bond' guarantees:

  7. 7 / 60

    Extra work beyond the contract scope should be authorized by:

  8. 8 / 60

    In the critical path method, a delay in one of the tasks on the key path through the network will:

  9. 9 / 60

    On a balance sheet, the assets are on one side and the liabilities plus stockholders' (owners') equity are on the other. The two sides are:

  10. 10 / 60

    According to the CSLB law book, a low ratio of net sales to net working capital might be attributed to:

  11. 11 / 60

    The CSLB law book says the labor percentage (direct labor as a share of the total cost) is a direct measurement of:

  12. 12 / 60

    The CSLB law book says the typical contract pays 90 percent during the construction phase and the final 10 percent:

  13. 13 / 60

    Which type of bond, as classified in the CSLB law book, guarantees both job completion and payment of all labor and materials?

  14. 14 / 60

    A bank loan officer reviewing a contractor's bid asks: Are completion dates realistic? Is there a chance that penalties will be assessed for delays? Under the CSLB law book, these questions evaluate the contractor's:

  15. 15 / 60

    Expenses of a general nature that cannot be specifically attributed to individual construction projects are reported on the income statement as:

  16. 16 / 60

    Using selling price = cost + (cost × markup percent ÷ 100), a job costing 1,000 dollars with a 25 percent markup sells for:

  17. 17 / 60

    In the CSLB law book, net profit for the year (often called net income) represents:

  18. 18 / 60

    Under the cash basis of accounting, revenue is recognized when:

  19. 19 / 60

    An electrical subcontractor completes its phase early in a long project. According to the CSLB law book, its retentions are released:

  20. 20 / 60

    Under Civil Code 9550, a direct contractor awarded a public works contract involving more than $25,000 must, before starting work, give a:

  21. 21 / 60

    On a contractor's income statement, which cost is usually the largest single expense item?

  22. 22 / 60

    The CSLB law book warns that differences in the timing of expenditures and receipts may limit a contractor's capacity to finance the business, particularly if the company:

  23. 23 / 60

    The third major financial statement, which shows how funds were obtained and where funds were used, is the:

  24. 24 / 60

    The CSLB law book describes fuel and lubricant expenses, general maintenance, and small tools as:

  25. 25 / 60

    The CSLB law book says that after all costs, including overhead, have been totaled in a bid, the contractor must add:

  26. 26 / 60

    The bar chart is a fundamental scheduling technique that shows the starting and finishing times of each task. Its weakness, according to the CSLB law book, is that it:

  27. 27 / 60

    The CSLB law book describes retention withheld from your progress payments as an amount that you have:

  28. 28 / 60

    'Labor burden' is:

  29. 29 / 60

    Working capital equals current assets minus:

  30. 30 / 60

    The CSLB law book says subcontractors should be chosen based on:

  31. 31 / 60

    According to the CSLB law book, the Small Business Administration (SBA) helps a contractor obtain financing because it will:

  32. 32 / 60

    Money supplied by investors who acquire some control of the business and a share of future profits is called:

  33. 33 / 60

    According to the CSLB law book, insufficient profits in a bid threaten both:

  34. 34 / 60

    Using quick assets = total current assets − inventories, and quick ratio = quick assets ÷ total current liabilities, a contractor with 300,000 dollars of current assets, 120,000 dollars of inventories, and 200,000 dollars of current liabilities has a quick ratio of:

  35. 35 / 60

    In a home improvement contract, BPC 7159 requires the scope of work to appear under the heading:

  36. 36 / 60

    Under California law, a public-works payment bond must be written in an amount not less than what portion of the total amount payable under the contract?

  37. 37 / 60

    The CSLB law book says the cash basis of accounting is not recommended for contractors. The accrual basis it describes instead recognizes revenues:

  38. 38 / 60

    Once construction begins, the CSLB law book says the estimate that is the basis for the bid becomes:

  39. 39 / 60

    Using current ratio = total current assets ÷ total current liabilities, a contractor with 300,000 dollars in current assets and 200,000 dollars in current liabilities has a current ratio of:

  40. 40 / 60

    On the balance sheet, fixed assets such as construction equipment are valued at:

  41. 41 / 60

    Billing is not the same as being paid. Under Civil Code 8800, unless otherwise agreed in writing, the owner must pay the direct contractor an undisputed progress payment within how long after the payment demand is given?

  42. 42 / 60

    A profit-and-loss (income) statement shows:

  43. 43 / 60

    'Retention' (retainage) is:

  44. 44 / 60

    Notes or mortgages due one year beyond the balance sheet date are classified as:

  45. 45 / 60

    When material prices from published price lists and supplier quotes are entered on the estimate form, the CSLB law book says it is important to include:

  46. 46 / 60

    The balance sheet section that represents the claim of the owners on the assets of the business is the stockholders' equity section, also called:

  47. 47 / 60

    Using retained earnings = total corporation earnings since its beginning − total dividends declared, a corporation that has earned 300,000 dollars since it was founded and has declared 240,000 dollars in dividends has retained earnings of:

  48. 48 / 60

    On the balance sheet, insurance premiums and office supplies that the company buys and pays for before use are listed as:

  49. 49 / 60

    A contractor with a performance bond has abandoned the job. According to the CSLB law book, the bonding company has the option of:

  50. 50 / 60

    Under Civil Code 2787, the party who promises to answer for the debt, default, or miscarriage of another is the:

  51. 51 / 60

    Using working capital = total current assets − total current liabilities, a contractor with 420,000 dollars of current assets and 260,000 dollars of current liabilities has working capital of:

  52. 52 / 60

    On the income statement, permits, bonds, and equipment rentals that are directly chargeable to individual jobs are reported as:

  53. 53 / 60

    When an estimator calculates labor costs according to work classification for a bid, the CSLB law book says those costs include the hourly wage rate and also:

  54. 54 / 60

    Current assets are cash or assets capable of being converted into cash in the normal course of business, generally within what period from the date of the balance sheet?

  55. 55 / 60

    In an estimate, 'overhead' refers to:

  56. 56 / 60

    Money a contractor owes to its suppliers and subcontractors is shown on the balance sheet as:

  57. 57 / 60

    Your electricians belong to a union. According to the CSLB law book, your direct labor burden will then also include:

  58. 58 / 60

    Using the percentage of completion method (profit earned = total estimated profit × percent complete ÷ 100), a job with a total estimated profit of 40,000 dollars that is 50 percent complete at year end has earned profit of:

  59. 59 / 60

    Under the completed contract method, a contractor reports the gross income and related costs for each contract:

  60. 60 / 60

    A bank loan officer deciding whether to recommend a line of credit (short-term loan) for a contractor would be interested in: