Free C-10 Practice Questions: Lien Law

60 free questions with answers, explanations and the source for each. Answer one to see why. No sign-up.

0 of 0 right · 60 to go
  1. 1 / 60

    What is the main effect of recording the notice of pendency (lis pendens) with the foreclosure suit?

  2. 2 / 60

    The amount of a California design professional's lien is limited to:

  3. 3 / 60

    If a genuine good-faith dispute exists over a private-works progress payment, how much may the owner withhold from the direct contractor without triggering the prompt-payment penalty?

  4. 4 / 60

    A claimant who WILLFULLY includes in the lien claim labor or materials that were never actually furnished to the property:

  5. 5 / 60

    Under Civil Code 8180, when no notice of cessation is recorded and the owner has not occupied the project, completion of a work of improvement occurs upon cessation of labor for a continuous period of:

  6. 6 / 60

    If no foreclosure lawsuit is filed within that period, the lien:

  7. 7 / 60

    The 20-day period for serving a preliminary notice is measured from the date the claimant:

  8. 8 / 60

    A supplier has already received and cleared a progress payment, and the general contractor asks for a release covering that amount. The correct statutory form is the:

  9. 9 / 60

    To free property from a recorded mechanics lien, the owner may record a lien release bond of ___ of the claim:

  10. 10 / 60

    Besides the price estimate and work description, a preliminary notice must identify the jobsite by:

  11. 11 / 60

    For priority purposes, the mechanics lien is said to 'relate back' to which date?

  12. 12 / 60

    A recorded construction deed of trust is generally SUBORDINATE to (junior to) mechanics liens if the deed of trust attached after which event?

  13. 13 / 60

    A 'Notice of Cessation' may be recorded after work has stopped continuously for:

  14. 14 / 60

    The surety bond accompanying a bonded stop payment notice is conditioned so that, if the claimant does not prevail, it will pay the costs and damages awarded to:

  15. 15 / 60

    An electrical subcontractor serves its preliminary notice and also files a copy with the county recorder. Under Civil Code 8214, the benefit of filing is that the county recorder will:

  16. 16 / 60

    The penalty for wrongfully withholding a construction payment under California's contractor prompt-payment statutes (B&P §7108.5 and Public Contract Code §7107) is:

  17. 17 / 60

    If a claimant records a mechanics lien but never files a lawsuit to foreclose it within the required time, the property owner may:

  18. 18 / 60

    A construction lender that receives an UNBONDED stop payment notice from a claimant:

  19. 19 / 60

    In an action to recover a wrongfully withheld payment, the prevailing party may recover:

  20. 20 / 60

    To preserve a payment bond claim, a claimant who was required to give it must still serve:

  21. 21 / 60

    An 'unconditional' waiver and release becomes effective:

  22. 22 / 60

    A public works payment bond must be in an amount of at least:

  23. 23 / 60

    The California design professional's lien (Civil Code 8300 et seq.) is available to which of the following, provided there is a written contract with the landowner?

  24. 24 / 60

    A BONDED stop payment notice (to force a construction lender to withhold) requires a surety bond equal to:

  25. 25 / 60

    A general contractor who holds a direct contract with the owner is required to give a preliminary notice to whom?

  26. 26 / 60

    After filing the lawsuit to foreclose a mechanics lien, the claimant must record a notice of pendency of action (lis pendens) within:

  27. 27 / 60

    Under the "Exceptions" heading of the Civil Code 8132 conditional waiver and release on progress payment, the form leaves untouched the claimant's rights to:

  28. 28 / 60

    When an owner wrongfully withholds a private-works progress payment from the direct contractor, the statutory penalty (in place of ordinary interest) is:

  29. 29 / 60

    A claimant who serves a stop payment notice on the construction lender (rather than the owner) attaches a surety bond mainly because:

  30. 30 / 60

    After recording a mechanics lien, the claimant must file a lawsuit to FORECLOSE it within:

  31. 31 / 60

    When there is a good-faith dispute over payment, the payer may withhold up to:

  32. 32 / 60

    Which item must a preliminary notice contain?

  33. 33 / 60

    On public works, the prime contractor must pay a subcontractor within ___ of receiving payment:

  34. 34 / 60

    On public works, retention must generally be released within ___ after completion:

  35. 35 / 60

    A 'mechanics lien' is:

  36. 36 / 60

    Before a design professional may record a design professional's lien on the site, what must have been obtained in connection with the design services?

  37. 37 / 60

    For all the work a supplier furnishes to a single work of improvement under one contract, how many preliminary notices must it give to each required recipient?

  38. 38 / 60

    You are requesting a progress payment that you have yet to receive. The statutory waiver form to sign is the:

  39. 39 / 60

    You should sign an UNCONDITIONAL waiver:

  40. 40 / 60

    A recorded mechanics lien must state:

  41. 41 / 60

    The preliminary notice must be served on:

  42. 42 / 60

    Under Civil Code 8132, a required waiver and release on an unpaid progress payment that departs from the statutory form is:

  43. 43 / 60

    If the owner records a Notice of Completion, a DIRECT (prime) contractor must record within:

  44. 44 / 60

    A 'conditional' waiver and release becomes effective:

  45. 45 / 60

    A subcontractor is handed the final payment check at closing, but it has not yet cleared the bank. Before releasing its rights, the sub should sign a:

  46. 46 / 60

    A stop payment notice is a claim against:

  47. 47 / 60

    A material supplier who sells to a subcontractor (not directly to the owner):

  48. 48 / 60

    For a claimant required to give it, compliance with the preliminary-notice requirement is:

  49. 49 / 60

    To serve a stop payment notice, a claimant who was required to give it must generally have first served:

  50. 50 / 60

    In a lawsuit to collect a private-works payment that was wrongfully withheld, what may the prevailing party recover in addition to the amount owed?

  51. 51 / 60

    On a private project, once a direct contractor receives a progress payment, within how many days must it pay a subcontractor the portion due for that subcontractor's completed work?

  52. 52 / 60

    An honest, innocent error in the amount or details stated in a recorded lien claim:

  53. 53 / 60

    To preserve lien rights, a subcontractor or supplier must serve a 'preliminary notice' within ___ of first furnishing labor or materials:

  54. 54 / 60

    An unpaid architect or engineer who provided design services under a written contract with the landowner may record a claim of lien as a:

  55. 55 / 60

    On a private job, a subcontractor's preliminary notice must be served on which parties?

  56. 56 / 60

    If the owner records a Notice of Completion, a SUBCONTRACTOR must record its lien within:

  57. 57 / 60

    The four statutory waiver forms are conditional and unconditional, each for:

  58. 58 / 60

    Under Civil Code 8200(e), which party on a private work of improvement is exempt from giving a preliminary notice?

  59. 59 / 60

    A mechanics lien attaches to:

  60. 60 / 60

    On a private work of improvement, an owner who has held back retention must release it to the direct contractor within how long after completion of the work?

← All free sections

C-10 guides, with the CSLB source

Help